Need help with these 2 questions about concrete if anyone can help me please!??
Q 1 - Following are the approximate quantities required for 1 m3 of concrete. Check the volumes and adjust, if required, to produce 1 m3.Cement 330
Q 1 - Following are the approximate quantities required for 1 m3 of concrete. Check the volumes and adjust, if required, to produce 1 m3.
Cement 330 kg
Water 195 kg
Fine aggregate 730 kgRD 2.68
Coarse Aggregate1250 kgRD 2.64
Air 3.5 %
Q 2 – A concrete plant uses the following quantities of materials per cubic metre of concrete,
Cement 310 kg
Water 180 kg
Fine aggregate 750 kg
Coarse Aggregate1080 kg
The concrete is mixed in batches of 3.5 m3. Find the mass of each material required per batch if the fine aggregate contains 4.0 % excess water.
What will the W / C ratio be ?
or:Q 1 - Following are the approximate quantities required for 1 m3 of concrete. Check the volumes and adjust, if required, to produce 1 m3.Cement\u200b 330 kgWater\u200b 195 kgFine aggregate\u200b 730 kg\u200bRD 2.68Coarse Aggregate\u200b1250 kg\u200bRD 2.64Air\u200b 3.5 % Q 2 \u2013 A concrete plant uses the following quantities of materials per cubic metre of concrete,Cement\u200b 310 kgWater\u200b 180 kgFine aggregate\u200b 750 kg\u200bCoarse Aggregate\u200b1080 kg\u200b The concrete is mixed in batches of 3.5 m3. Find the mass of each material required per batch if the fine aggregate contains 4.0 % excess water. What will the W / C ratio be ?